SAWFACE facility: scheduling operation in 2019

Picture
If you are interested in carry out any research in the SAWFACE facility during 2019, now is the time to contact us in order to program the scheduling operation during the next growing cycle.

  • December-2018 and January-2019: reception of proposal for research opportunities
  • January and February 2019: calibration and maintenance operations; preparation of experimental area
  • February: filling of the CO2 deposit
  • 1-10-March 2019: first test of operation at target CO2= 550 ppm
  • 1-15-March-2019: installation of external experiments
  • 15-March-2019: fertilization period starts
  • 15-April-2019: first stop for maintenance and calibration
  • 15-May-2019: second stop for maintenance
  • 15-June-2019: third stop for maintenance and calibration
  • 10-15-July: filling of the CO2 deposit
  • 15-July-2019: fourth stop for maintenance
  • 15-August-2019: fifth stop for maintenance and calibration
  • 15-September-2019: sixth stop for maintenance
  • 15-October-2019: end of the fertilization period